Martin Marietta

Control Room Remodel for a Manufacturing Plant

A 6,500-square-foot second-floor control room remodeled inside an active manufacturing plant in Midlothian, Texas — delivered in 2.5 months without shutdowns or interruptions to ongoing plant operations.

Client

Martin Marietta

Location

Midlothian, TX

Footprint

6,500 sq ft

Duration

2.5 months

Martin Marietta - Control Centre Manufacturing Plant (6,500sqft): Project Completed - Image4

Midlothian, TX

02 Coordinated Execution for a Safe, On-Time Remodel

Overcoming Access, Safety, and Scheduling Challenges in an Active Plant

01

Construction work had to be completed while the manufacturing plant remained fully operational.

02

The remodel was performed on the second floor, creating logistical and access challenges for material movement and construction activities.

03

Existing structural platforms required onsite modifications to support new installation requirements.

04

Additional second-floor access required exterior metal work and coordination within the active facility.

05

Multiple trades, including architectural finishes, technology systems, structured cabling, and FF&E, had to be carefully coordinated within an accelerated schedule.

06

All supervisors were required to be MSHA-certified and follow strict safety and operational protocols throughout the project.

07

Continuous coordination with the project owner was required throughout each stage of the design process, with supervisors actively involved in approvals, progress discussions, and decision-making to keep the project aligned.

08

The timeline was almost 2.5 months, requiring precise coordination to avoid delays or disruptions to plant operations.

Martin Marietta - Control Centre Manufacturing Plant (6,500sqft): Project Completed - Image6

03 The Solution

Coordinated Execution for a Safe, On-Time Remodel

To complete the remodel without disrupting plant operations, the project was carefully planned and completed in phases. The team coordinated closely with Martin Marietta facility personnel and onsite teams to manage daily work activities, material movement, safety access, and construction logistics. Because the remodel was located on the second floor, special attention was given to access and material handling. Exterior metal work was completed to add dedicated second-floor access, including a new entrance and staircase. Interior work, technology systems, structured cabling, MEP upgrades, and FF&E were coordinated to keep the project moving efficiently within the accelerated schedule. All supervisors were MSHA-certified and adhered to strict safety and operational protocols throughout the project. Because the work took place in an MSHA-regulated facility, safety and coordination were critical at every stage. The project involved 9–10 supervisors from our team, all of whom were MSHA-certified and responsible for maintaining strict safety, scheduling, and operational standards throughout the project.

04 Project Result

6,500 square feet, delivered in 2.5 months — on schedule, fully operational, with the plant running every day of the build.

Through careful planning, communication, and phased execution, the team completed the 6,500-square-foot control room remodel on time within the 2.5-month schedule, while the manufacturing plant remained fully operational. Each stage of the project was reviewed and approved in coordination with the project owner to ensure the final outcome aligned with operational requirements, quality expectations, and overall client satisfaction.

6,500

Sq Ft Delivered

2.5

Months on Site

ZERO

Plant Shutdowns

05 Project Completion

From construction progress to a
finished, functional space.

Completed project images showcase the finished control room facility, highlighting the fully functional, furnished, and ready-to-use space delivered successfully.
Before
After
Raw shell · exposed structure
Martin Marietta - Control Centre Manufacturing Plant (6,500sqft): Project Completed - Image4
Operational · finishes, MEP, technology, FF&E

Explore Our Industrial Construction Service Areas

Building on our experience with projects like Martin Marietta in Midlothian, Arrant Construction provides industrial construction and facility improvement services across Texas. Explore our services in Dallas, Fort Worth, Houston, Austin, San Antonio, Irving, Richmond, and other Texas markets for support with industrial renovations, operational upgrades, and complex facility construction.

Next

Have a project that can't stop running?

Scroll to Top
Fill out the form and get in touch with our construction experts.